Difference in Orginal duration

Member for

16 years 1 month

Hai Artagnan

I updated Program Manually..

Regards
Arun

Member for

17 years 1 month

Arun,

How did you update the program? Manually or some external application such as excel or SDK?

 

 

Member for

17 years 1 month

Arun,

How did you update the program? Manually or some external application such as excel or SDK?

 

 

Member for

21 years 8 months

Maybe it is because WBS duration is a calculated value (*) and not a fixed entry is why it behaves in this way.

I can think of two workarounds.

Use global change and store original duration as a user defined field, in this way it will be frozen at the activity level as well as at the WBS level, verify on this as I am not a P6 user, I am applying what I recall from my previous use of P3e, P3 and SureTrak.

Store your initial job as a baseline and on updates display baseline original duration next to current schedule original duration.

Hope this helps.

Member for

16 years 1 month

Hai Friends

Any experts to answer my above question????

regards
Arun