I agree with Alex. You need to find out the exact requirement from client. Such enterprise integration various from business to business.
P3e HR Resource pool can be integrated with SAP-HR.
As per my recent experience with client. We have integrated SAP-FICO with P3e. The final report client can get out of this integration is called accrual report i.e. difference between SAP Actual and P3e Actuals. Remember both are different.
If you need any input on Primavera API side, feel free to ask.
I had a software developer working on this at present and it seem to be on track
Because he had implemented P3e/c and Teamplay with MIMS and SAP before & I am the project manager for the implementation and roll out.
Since both platform is on Oracle the development is kind of ok but... the API rules is the biggest difficulty.
We implemented in two different approach.
First is transaction by transaction... the amount is data is huge
Another way is by summary , it is a lot easier and the integration time is a lot faster.
Depend on what module you actual want to integrate with SAP the level of difficulty vary.
With PM module - if you need to track the assets ID and cost
With HR module - if you want to track hrs and skill
With PS module - if you want to track project orientated info...
With FC module - cost only
Ask your client what exactly they want, entreprise reporting system or project management system or entreprise resource planning or assets investment / return or the lot.
Member for
20 years 11 monthsRE: P3e SAP Systems Integration
I agree with Alex. You need to find out the exact requirement from client. Such enterprise integration various from business to business.
P3e HR Resource pool can be integrated with SAP-HR.
As per my recent experience with client. We have integrated SAP-FICO with P3e. The final report client can get out of this integration is called accrual report i.e. difference between SAP Actual and P3e Actuals. Remember both are different.
If you need any input on Primavera API side, feel free to ask.
Happy Integration.
Member for
22 years 8 monthsRE: P3e SAP Systems Integration
I had a software developer working on this at present and it seem to be on track
Because he had implemented P3e/c and Teamplay with MIMS and SAP before & I am the project manager for the implementation and roll out.
Since both platform is on Oracle the development is kind of ok but... the API rules is the biggest difficulty.
We implemented in two different approach.
First is transaction by transaction... the amount is data is huge
Another way is by summary , it is a lot easier and the integration time is a lot faster.
Depend on what module you actual want to integrate with SAP the level of difficulty vary.
With PM module - if you need to track the assets ID and cost
With HR module - if you want to track hrs and skill
With PS module - if you want to track project orientated info...
With FC module - cost only
Ask your client what exactly they want, entreprise reporting system or project management system or entreprise resource planning or assets investment / return or the lot.
Cheers
Alex