How to consider miscellaneous costs, and resources

Member for

19 years

Shareef,

If the resource is under WBS summary activities or Level of effort activities, you can change the planned date of each resource so the distribution of cost will be based on the estimated planned date. If the activities are sitting at one WBS then use WBS summary activities otherwise use LOE (same as hammock) and link the first activity SS and last Activity FF and assign resource. See sample below:

Resource Allocation

Member for

20 years 1 month

Thanx once again Rodel,



You are the P6 user manual for a lot of planners...



Now I would like you to detail your reply



LOE activities are Level of Effort I guess. Is it similar to hammock activity?



"You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource".



can you clarify the above a little more in detail?



( WBS summary activities???.... change planned date for each resource???)



Hope youll have the patience!!!



Thank you once again Rodel

Member for

19 years

Shareef,

You can use LOE activities and assigned expenses, misc materials, sundries...etc...where applicable if you don’t have designated activities for those item. You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource.