If the resource is under WBS summary activities or Level of effort activities, you can change the planned date of each resource so the distribution of cost will be based on the estimated planned date. If the activities are sitting at one WBS then use WBS summary activities otherwise use LOE (same as hammock) and link the first activity SS and last Activity FF and assign resource. See sample below:
Member for
20 years 1 month
Member for20 years2 months
Submitted by Shareef Abdul Azeez on Mon, 2010-07-19 13:20
You can use LOE activities and assigned expenses, misc materials, sundries...etc...where applicable if you dont have designated activities for those item. You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource.
Member for
16 years 5 monthsRE: How to consider miscellaneous costs, and resources
Thanks Rodel so much, this subject was my headache for a long time, but now, no more.
Thanks Shareef for rising this subject.
Duy
Member for
20 years 1 monthRE: How to consider miscellaneous costs, and resources
Thanx Rodel
Now I understand!!!
Member for
19 yearsRE: How to consider miscellaneous costs, and resources
Shareef,

If the resource is under WBS summary activities or Level of effort activities, you can change the planned date of each resource so the distribution of cost will be based on the estimated planned date. If the activities are sitting at one WBS then use WBS summary activities otherwise use LOE (same as hammock) and link the first activity SS and last Activity FF and assign resource. See sample below:
Member for
20 years 1 monthRE: How to consider miscellaneous costs, and resources
Thanx once again Rodel,
You are the P6 user manual for a lot of planners...
Now I would like you to detail your reply
LOE activities are Level of Effort I guess. Is it similar to hammock activity?
"You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource".
can you clarify the above a little more in detail?
( WBS summary activities???.... change planned date for each resource???)
Hope youll have the patience!!!
Thank you once again Rodel
Member for
19 yearsRE: How to consider miscellaneous costs, and resources
Shareef,
You can use LOE activities and assigned expenses, misc materials, sundries...etc...where applicable if you dont have designated activities for those item. You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource.