Oracle Primavera - PM6 Member for 19 years 5 months Member for 19 years 5 months Submitted by Richard Hill on Mon, 2008-06-30 06:20 Permalink RE: Planned Dates = Start and Finish Dates Apologies no need for reply back. I figured it out in the end! Wasnt what I expected but I entererd Start is Greater than or Equal to PS and Finish is Less than or eEqual to PF > Then Planned Start is Equal to Start and Planned Finish is Equal to Finish. Log in or register to post comments
Member for 19 years 5 months Member for 19 years 5 months Submitted by Richard Hill on Mon, 2008-06-30 06:20 Permalink RE: Planned Dates = Start and Finish Dates Apologies no need for reply back. I figured it out in the end! Wasnt what I expected but I entererd Start is Greater than or Equal to PS and Finish is Less than or eEqual to PF > Then Planned Start is Equal to Start and Planned Finish is Equal to Finish.
Member for
19 years 5 monthsRE: Planned Dates = Start and Finish Dates
Apologies no need for reply back.
I figured it out in the end! Wasnt what I expected but I entererd
Start is Greater than or Equal to PS and
Finish is Less than or eEqual to PF
> Then Planned Start is Equal to Start and
Planned Finish is Equal to Finish.