Productivity factor in P5

Member for

17 years 8 months

You need to use Global Chaneg .



And select Activity Resource Assignment .



Change Budgeted units for All REsources from 1 to 1.15



regards



shiv

Member for

18 years

Sorry but you need to input the new figures (+15%) manually...



Good day

Member for

23 years 11 months

You can try increasing resource max units/time to 115% and recalculate.