Hi,

Thanks everyone for your reply.



What do you mean by "Update Progress" is subjective? Is "Update Progress" and "Schedule" different?? In what sense?



The global change somewhat solve the problem, thanks.



The "fill-down" function did great but it is very annoying when it keep on asking me 70+ times if I want to make the task to "not started" because there are some actuals on it. How to skip those annoying questions?!!


Member for

18 years 9 months

Yusuke

1: If you call this function and then click onto the Help-Button you’ll get good information. Be aware that the algorithm (the way how it calculates) is different to P3.

2 and 3: It’s at least as easy as in MSP. Add "actual start" to the columns --> delete the entry within the upmost activity --> select all and PAY ATTENTION! with the cursor within that column --> click right mouse button --> "Fill down".

4. Ask your boss to let you join a training.

Regards

Dieter

Member for

19 years 1 month

1. "update progress" is subjective; F9 is a single function of the program (meaning you run or calculate the schedule)



2. & 3. use global change