How do we know What is the Proj. % Comp ? IN P6

Member for

19 years 3 months

Alex,

Its not shortcutting. Our company doesnt want to put the costing for resource. And also they do give the % complete on basis of physical justification.


Member for

22 years 9 months

Suresh



Yep the prolem is how the scheduler/planner do not want to do his/her job properly.



There is no short cut in life, resource load your schedule and either use cost or resource unit to calculate your % complete



Good Luck



ALex