Budgeted units = actual units

Member for

18 years 9 months

Naveen

Open "Tools" --> "Global Change" --> "New" --> select "Activity Resource Assignments" --> Give a name to this global change --> lines as indicated.

I have the impression that you are not familiar with the Global Ghange, so after you will have selected "New" you’ll select "Help" first. The description is very good.

If you’ll have any difficulties, write a private message.

Good luck

Dieter

Member for

20 years 10 months

Dieter,



I cannot put actual finish NOT EQUAL TO because I mentioned earlier that these activities have actual finish dates but the resource units have not been updated (For example if the budgeted units were 100 then actual units are left as 0). Only start & finish has been updated & this is causing the unit % complete at summary level to be very low. I tested this on a small project with 5 activities & the result has been the same.



Alex,



Its in normal gantt chart veiw.



Regards

Naveen

Member for

22 years 9 months

Hi



When you mentioned summary level, do you mean @ tracking view and project view. If it is, then its simple, you need to run project summarisation to update these details to the project level.



HTH



Alex

Member for

18 years 9 months

Naveen

Sorry, my mistake:

If actual finish NOT EQUAL

Actual this period labor units = Budgeted labor units

Regards

Dieter

Member for

18 years 9 months

Naveen

please explain what is working, and where are different result to your expectations.

Explain your steps please.

Regards

Dieter

Member for

18 years 9 months

Naveen

Global change is the right idea:

- Group ("Activity Resource Assignments")

- If actual finish >

- Actual this period labor units = Budgeted regular labor units

Please check the list before commitment. No warranty, I don’t belong to Primavera - just a user

Hope this will help

Dieter