You cannot display or show the Data Value in the Resource Histogram. If you wish to know the Value just double click on the Histogram and it will give you the Budgeted, Actual & Remaining Value.
Thanks..
Arnold
Member for
19 years 9 months
Member for19 years9 months
Submitted by Ahmed Saudagar on Mon, 2008-05-05 09:03
In P3, when you go to Tools-Grapic Reports-Resource &Cost and select to open any report and open Contents TAB, at the bottom in the center you will find under Histogram DISPLAY DATA VALUES option. This option when checked will provide a data figure/value on top of the histogram week/month when printed.
I want to know where I can find this option in P6.
I get the resource histogram but am not able to find it.
Member for
19 years 9 monthsRE: Data Value in Resource Histogram in P6
Thanks guys for your quick and responses and valuable tips.
Member for
18 years 1 monthRE: Data Value in Resource Histogram in P6
Hi.
P6 does not support this feature.
You can do it in Primavera chart module. Its sold seperately.
Member for
18 years 6 monthsRE: Data Value in Resource Histogram in P6
Hi Ahmed,
You cannot display or show the Data Value in the Resource Histogram. If you wish to know the Value just double click on the Histogram and it will give you the Budgeted, Actual & Remaining Value.
Thanks..
Arnold
Member for
19 years 9 monthsRE: Data Value in Resource Histogram in P6
Hi K D
In P3, when you go to Tools-Grapic Reports-Resource &Cost and select to open any report and open Contents TAB, at the bottom in the center you will find under Histogram DISPLAY DATA VALUES option. This option when checked will provide a data figure/value on top of the histogram week/month when printed.
I want to know where I can find this option in P6.
I get the resource histogram but am not able to find it.
Hope this better explains to the problem.
Member for
18 years 1 monthRE: Data Value in Resource Histogram in P6
Hi Ahmed.
Could you elaborate your query ? We can not get it so far.