- no actual units: just replace A by B (icon just above the help sign within the assign resources window)
- With actual units: The most accurate would be: Put an end-date to the assignment and make a new one with the new resource. To replace A by B, youll have to remove the actual units first - and later assign them to the new resource.
Hope this will help
Regards and a nice "day of work"
Dieter
Member for
23 years 11 months
Member for23 years11 months
Submitted by David Forrest on Wed, 2008-04-30 08:39
All i want to know is how can replace one resource with another in the middle of a project.
Eg:
Software Engineer (Jose) is assigned for acivity 01 . When duration of the task became 50% he left job. Now i want use another guy (Eg: Alex) in replacement of jose. How can i make it possible without affecting the performance % complete or some other crap result.
Hope you got my qstn.
Cheers
Suresh
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Wed, 2008-04-30 06:28
I dont really understand your question: Labour worked e.g. 6 hours and now you say the fitter was it? Then youll remove the actual units --> replace by fitter --> assign the actual units again --> Schedule. In reports youll find the actuals under the data date.
Within the window "Assign resources" youll find the icon on the right side.
Member for
18 years 9 monthsRE: RESOURCE REPLACEMENT IN P5
Sorry David
I couldnt see your answer when I wrote mine
Regards
Dieter
Member for
18 years 9 monthsRE: RESOURCE REPLACEMENT IN P5
Hi Suresh
It depends on the actuals:
- no actual units: just replace A by B (icon just above the help sign within the assign resources window)
- With actual units: The most accurate would be: Put an end-date to the assignment and make a new one with the new resource. To replace A by B, youll have to remove the actual units first - and later assign them to the new resource.
Hope this will help
Regards and a nice "day of work"
Dieter
Member for
23 years 11 monthsRE: RESOURCE REPLACEMENT IN P5
Assign second resource and allocate remaining days, remove remaining days from original resource.
Member for
19 years 3 monthsRE: RESOURCE REPLACEMENT IN P5
Hi Diater,
Sorry if the qst made you confused.
All i want to know is how can replace one resource with another in the middle of a project.
Eg:
Software Engineer (Jose) is assigned for acivity 01 . When duration of the task became 50% he left job. Now i want use another guy (Eg: Alex) in replacement of jose. How can i make it possible without affecting the performance % complete or some other crap result.
Hope you got my qstn.
Cheers
Suresh
Member for
18 years 9 monthsRE: RESOURCE REPLACEMENT IN P5
Hi Suresh
I dont really understand your question: Labour worked e.g. 6 hours and now you say the fitter was it? Then youll remove the actual units --> replace by fitter --> assign the actual units again --> Schedule. In reports youll find the actuals under the data date.
Within the window "Assign resources" youll find the icon on the right side.
Was this your question?
Regards
Dieter