P5 Allocation Limit

Member for

18 years 1 month

Hi.

Allocation limit is set when you use "Planning resource" function (only available in Web module).

Member for

18 years 8 months

Bryan,

What allocation Limit?



Resource Availability, Role Quantities??



Also were you aware that in P5 the Web - My Primavera only uses summarised data.



So you should have a job service set up to summarise your projects each night. Also you should set your ’Level of Summarisation’ at the project level somewhat lower than the ’2’ default if your after any sort of detail.



Andy