Level of effort activity’s actual progress

Member for

23 years

Use a Global Change



You will need to use 2 action statements, one to do the Actual/At Completion part and then another to multiply this result by 100 to arrive at a percentage value.

Member for

20 years 7 months

Thanks. But in this case I need to manually calculate the progress every time I update the schedule



My target is to set the level of effort activity to automatically calculate progress as follows:

Activity % Complete = Actual duration / At Completion duration.