Level of Effort and Critical Path

Member for

19 years 6 months

Just a last note; have you tried using a WBS Summary task? It mimics a WBS parent without being one AND can be on the Critical Path.

Member for

18 years 8 months

Gordon .... thanks for the tip on P6, it’s been quite annoying for years that a rollup has to be done again and again ........

Member for

18 years 8 months

Thanks guys, a colleague said I could drive the colour through coding. This is the best way forward for me now (even though I may have to revert to the WBS option - Plan B!!).



And I am trying to do it using the Activity ID but the filter changes ALL the LOE activity colours. How can I isolate just 1 activity? Also everytime I run the filter and then go back in ALL the settings go back to "all activities" ie it loses the settings I want and goes to default ..... why is that?

Member for

22 years 9 months

Hi



LOF is same as the old "Hammock" activity, it provide the summary effort of the linked activity, however, it cannot be a critical because simply is id not form part of the detail critical path.



To achieve what you wanted in a report format you can use coding to drive the LOE activities to turn RED color.



HTH



Alex

Member for

20 years 3 months

Dean,



I tend to just use the WBS, run a rolled up layout and where the WBS contains critical activities, they will show on the summary bar.



[The benefit of P6 being that you can save the ’roll-up level’ when you save the layout]

Member for

18 years 8 months

Hi, I’d like to know more about establishing a critical path using LOE bars. For example in a programme that has 1000+ activities that role up to say 50 LOE’s - it may be useful to show which LOE’s are ’representing’ critical activities



I’ve looked at creating a ’New’ LOE bar (with a filter) to go with the Remaining and Actual LOE’s - this looks tricky and may not be possible, before I waste a week doing this, has anyone else tried and succeeded????

Member for

18 years 6 months

Hi Seb,



As you said you have a Level OF Effort Activity,



Level of effort is not part o your critical path becouse its duration is defined base on your critical path Duration,

As an example , you have a project and you have security guard on site , you could not say Security guard is part of your Critical Path, becouse the duration of Perform security task is depend on your project Duration , the same for Services , Supervision ( In some cases) , PMO Offic





Good Luck



Hamed