Project Mananger, Siemag Tecberg, Mine Winder

START Date: 
March, 2014
END Date: 
November, 2015

 

 

ØDevelop project proposals, ensure estimates have the required accuracy and obtain approval;

ØCoordinate personnel in controlling the value, cost and schedule of the project;

ØCoordinate the staffing of the project team which varies over the time of the project;

ØNegotiate arrangements for design with engineering consultants, internal and external;

ØCoordinate the preparation of documentation for manufacturing and construction bidding. Participate in the selection process and recommend contractors;

ØEstablish team on site and coordinate the construction, startup and commissioning of the project deliverables;

ØApprove contract variations and payments within authority;

ØGuide and direct personnel in the application of specific government and industry standards;

ØPrepare a monthly reports showing status of design, material procurement, construction, milestones, payments, charges, variances and issues;

ØManage project risk. Anticipate and plan for changes in project scope, timing or costs;

ØClose out projects and facilitate lessons learned. Prepare post-implementation reports for management.

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
250