Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Victor Egnora's experience

Planning Manager, Mace International Ltd, Dubai Eye, Marsa Al Seef, SBJ Villa Projects-Oman, DWTC

Planning Manager, Mace International Ltd, Dubai Eye, Marsa Al Seef, SBJ Villa Projects-Oman, DWTC

START Date: 
May, 2015
  • Manage overall project planning & controlling process
  • Programme management and integration ensuring timely delivery of work packages
  • Oversee reporting, forecasts, and highlight project issues affecting progress
  • Provide advice to clients in matters relating to planning, scheduling, claims
  • Evaluate and advice clients in claims avoidance and claims defense
  • Developed Windows analysis both Prospective and Retrospective for the Client
  • In the absence of contemporaneous updates developed the As built monthly windows based on linear distribution of progress to the activities
  • Researched documents and developed Cause and Effect Analysis
  • Developed Fragnets and entered them in the updates assessing the time impact to the completion milestone under analysis
  • Identifies issues that adversely impact progress for coordination
  • Supported analysis with graphs, tables and presentations
  • Participated in meetings with all parties involved
  • Performed delay analysis for various projects in Dubai, Qatar and Oman
  • Evaluate subcontractor claims, formulate recommendations to the Client
Experience Hours (Planning & Scheduling): 
3300
Experience Hours (Cost Management): 
550
Experience Hours (Forensic Analysis): 
2000
Senior Planning Engineer / Delay Analyst, Schema Management Group, Dubai International Airport - Terminal 2

Senior Planning Engineer / Delay Analyst, Schema Management Group, Dubai International Airport - Terminal 2

START Date: 
April, 2015
END Date: 
August, 2014

1. Develop Windows Analysis both prospective and retrospective for the client

2. In the absence of contemporaneous updates, develop the monthly update windows based on linear distribution of progress

3. Research, cause and effect analysis

4. Develop fragnets and incorporate and use it to determine the impact of a delay event into the Time for Completion

5. Identifies issues that adversely impact progress for coordination

6. Manage the claims process

7 Attend claims meetings

8. Prepare delay analysis for the Dubai International Airport T2 using Time Slice method

Experience Hours (Planning & Scheduling): 
250
Experience Hours (Forensic Analysis): 
250
Senior planning Engineer, Ed Zublin AG, SHIEK ZAYED DESERT LEARNING CENTRE & UAE WORLD DESERT, NON-PROCESS PACKAGE OF RUWAIS REFINERY EXPANSION PROJECT

Senior planning Engineer, Ed Zublin AG, SHIEK ZAYED DESERT LEARNING CENTRE & UAE WORLD DESERT, NON-PROCESS PACKAGE OF RUWAIS REFINERY EXPANSION PROJECT

START Date: 
August, 2010
END Date: 
July, 2014
Responsibilities: 1. Formulates recovery schedule to recover lost time. 2. Define and coordinate specific activities and work tasks. 3. Assign and allocate resources to competing activities. 4. Updates construction / contract programme / recovery programme 5. Identifies issues that adversely impact progress for coordination 6. Generates progress status reports, production/cost reports, and earned value reports. 7. Attend coordination / progress meetings with client, consultants, and concerned parties 8. Perform delay analysis exercises – Time Impact, Time Slice Method, Impacted As-planned, As-built Critical Path
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
4000
Planning Engineer, DUTCO-Balfour Beatty, The Dubai Mall

Planning Engineer, DUTCO-Balfour Beatty, The Dubai Mall

START Date: 
February, 2007
END Date: 
July, 2010
Responsibilities: 1. Prepare macro & micro planning for the project. 2. Consolidates daily reports for analysis 3. Define and coordinate specific activities and work tasks. 4. Assign and allocate resources/cost to competing activities. 5. Updates construction programme, site level programme, and coordinated programme 7. Analyze the impact of delays to the programme and formulates recovery action 8. Generates progress status report, production/cost reports, and earned value reports. 8. Attend coordination meetings with site operatives, subcontractors, and package contractors 9. Responsible for updating the programme incorporating latest revisions, variations & changes 10. Assist the Specialist Forensic/Claims Consultants: a. Production of as-built programmes; b. Consolidation of contemporaneous records for analysis; c. Develop chronological narrative of delaying events based on contemporaneous records;
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Forensic Analysis): 
2000
Planning Engineer, Murray & Roberts Construction, DUBAI INTERNATIONAL AIRPORT FIT-OUT PROJECT Package AX059

Planning Engineer, Murray & Roberts Construction, DUBAI INTERNATIONAL AIRPORT FIT-OUT PROJECT Package AX059

START Date: 
September, 2005
END Date: 
February, 2007

PROJECT:    DUBAI INTERNATIONAL AIRPORT FIT-OUT PROJECT Package AX059

A 1.80 million square meter facility comprising terminal and concourse area, designed to boast the airport’s capability of handling 17 million passengers annually in line with the government’s vision to attract business and tourism in the region, Dubai being the center of economic activities in the coming years. Five (5) underground basements makes up the terminal area for arrivals and departures, the baggage handling system, the high speed passenger train, with provision for the Light Railway Transport. Apron, on the other hand is made up of lounges and hotels.

 

Project Cost: US 1B     

Responsibilities:

  • Prepare macro & micro planning for the project.
  • Consolidates daily reports for analysis.
  • Define and coordinate specific activities and work tasks.
  • Assign and allocate resources to competing activities.
  • Updates construction programme, site level programme, and coordinated programme
  • Analyze the impact of delays to the programme and formulates recovery action
  • Generates progress status report, production reports, and earned value reports.
  • Attend coordination meetings with site operatives, subcontractors, and other package

           contractors

Experience Hours (Planning & Scheduling): 
2700

Market Place