Planning Engineer, Bam International Abu Dhabi LLC, Premier Inn Hotel - Abu Dhabi; Externsion of Retail Corridor - Abu Dhabi Airport
START Date:
February, 2012
END Date:
March, 2014 Prepared baseline program; Prepared boq cost breakdown activity wise and loading baseline activities with cost and manpower resources; start-up programmes; setting up of progress measurement system including kpi’s and dashboard; preparation of engineering (shop drawing, material and method statement) schedules and long lead procurement schedules with respect to baseline programme; updating baseline programme and reviewing with project team; client progress report preparation;subcontractor program review and progress monitoring; prepared lookaheads programmes; prepared impacted programmes & delay analysis for extension of time claims.