ANALYST / PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection & WWTP
ANALYST / PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection & WWTP
START Date:
April, 2012 Project Planning, Executing, Monitoring & Control & Close out
- Review tender documents and prepare pre-contract planning package as per tender requirements
- Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
- Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
- Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
- Develop the WBS & WP (Scope baseline) to manage & control as per scope.
- Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI) and notify to the project manager to control the variance.
- I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
- Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
- Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
- Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
- Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
- Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
- Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
- Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
- Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
- Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
- Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
- Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
- Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule.
Reporting
- Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
- Prepare & submit the EVM report to the management
- Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
- Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
- Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
- Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.
ERP-Oracle-EBS
- Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
- Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
- Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
- Develop new reports as when required and randomly check the retained cost by finance department
- Highlight the ERP Project related issue to IT department
- Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling):
10000
Experience Hours (Cost Management):
10000
Experience Hours (Forensic Analysis):
6000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection
PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection
START Date:
April, 2012 Project Planning, Executing, Monitoring & Control (Time, Scope & Cost)
- Review tender documents and prepare pre-contract planning package as per tender requirements
- Attend the Kick-Off meeting and discuss the Deliverables, Milestones, Concern & Risk Area, Permit to Work (PTW) and etc.
- Prepare Clause 14/8.3 (Baseline) Program, Project Planning Procedure / Packages and obtain approval from client/engineer & identify the Critical Path activities & forecast critical path on as-built schedule and notify to the Project Manager to control the variance.
- Issue 2 weeks Look ahead, 1 Month Look ahead program & Internal target program to meet the progress & minimize the variance to the project team
- Load resource & cost on the baseline program to monitor the resources, cost & progress.
- Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
- Prepare Progress Measurement System (PMS), Equipment Resource Planning (ERP), Manpower Resource Planning (MRP), Cost Control Registry (CCR) & Progress S-Curve (Early Start & Late Start)
- Update Progress Measurement System (PMS) daily, measure the progress performance from SV & SPI and report to the project manager for further action on the delay.
- Identify the delays and prepare the recovery program by crushing or fast track activities to achieve to maintain the baseline WBS completion date.
- Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
- Responsible to plan the most efficient way to complete the project as scheduled and within the budget I developed the Cost Control Registry (CCR) along with EVM system and update by monthly and assess the CV, EAC, ETC, VAC & CPI & submit the EVM report to Project Manager & Higher Management.
- Review the subcontractor baseline schedule and monitor the progress and responsibility to accelerate the progress to complete the on schedule.
- Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
- Identify the Project Risk, prepare the Risk Management Plan & monitoring the registry monthly basis
- Plan the 3 month project wise revenue for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
- Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I used update the cash flow as per as-build schedule.
Reporting & Closure
- Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
- Prepare & submit the EVM report to the management
- Prepare & submit daily/ weekly progress summary report to the management.
- Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
- Prepare and handle all planning documents for Project Closure.
- Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow
- Prepare the company cost report and analyse the annual revenue & profit/loss from the project control department.
ERP-Oracle-EBS
- Responsibility to create the projects in the ERP-Project Modules, task as per WBS, assign the customer & project manager and create the cost budget for the project
- Give instruction to Supply Chain user to select the proper Item Code and Task to avoid wrong cost booking.
- Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
- Develop new reports as when required and randomly Check the cost booked by finance department
- Highlight the ERP Project related issue to IT department
- Close the project as per close-out transmittals to avoid to book the cost on the completed project.
Experience Hours (Planning & Scheduling):
10000
Experience Hours (Cost Management):
8000
Experience Hours (Forensic Analysis):
6000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP
START Date:
April, 2011 Project Planning, Executing, Monitoring & Control & Close out
- Review tender documents and prepare pre-contract planning package as per tender requirements
- Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
- Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
- Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
- Develop the WBS & WP (Scope baseline) to manage & control as per scope.
- Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI) and notify to the project manager to control the variance.
- I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
- Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
- Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
- Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
- Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
- Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
- Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
- Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
- Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
- Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
- Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
- Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
- Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule.
Reporting
- Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
- Prepare & submit the EVM report to the management
- Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
- Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
- Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
- Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.
ERP-Oracle-EBS
- Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
- Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
- Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
- Develop new reports as when required and randomly check the retained cost by finance department
- Highlight the ERP Project related issue to IT department
- Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling):
10000
Experience Hours (Cost Management):
10000
Experience Hours (Forensic Analysis):
6000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP
START Date:
April, 2011 Project Planning, Executing, Monitoring & Control & Close out
- Review tender documents and prepare pre-contract planning package as per tender requirements
- Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
- Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
- Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
- Develop the WBS & WP (Scope baseline) to manage & control as per scope.
- Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI) and notify to the project manager to control the variance.
- I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
- Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
- Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
- Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
- Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
- Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
- Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
- Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
- Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
- Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
- Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
- Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
- Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule.
Reporting
- Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
- Prepare & submit the EVM report to the management
- Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
- Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
- Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
- Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.
ERP-Oracle-EBS
- Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
- Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
- Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
- Develop new reports as when required and randomly check the retained cost by finance department
- Highlight the ERP Project related issue to IT department
- Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling):
10000
Experience Hours (Cost Management):
10000
Experience Hours (Forensic Analysis):
6000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP
START Date:
April, 2011 Project Planning, Executing, Monitoring & Control & Close out
- Review tender documents and prepare pre-contract planning package as per tender requirements
- Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
- Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
- Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
- Develop the WBS & WP (Scope baseline) to manage & control as per scope.
- Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI) and notify to the project manager to control the variance.
- I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
- Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
- Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
- Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
- Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
- Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
- Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
- Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
- Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
- Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
- Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
- Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
- Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule.
Reporting
- Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
- Prepare & submit the EVM report to the management
- Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
- Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
- Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
- Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.
ERP-Oracle-EBS
- Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
- Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
- Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
- Develop new reports as when required and randomly check the retained cost by finance department
- Highlight the ERP Project related issue to IT department
- Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling):
10000
Experience Hours (Cost Management):
10000
Experience Hours (Forensic Analysis):
6000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
PLANNING ENGINEER, ENERMES ENGINEERING QATAR W.L.L., Pearl Qatar (2B+G+21+R)-MEP Installation, VB 20 & 21
PLANNING ENGINEER, ENERMES ENGINEERING QATAR W.L.L., Pearl Qatar (2B+G+21+R)-MEP Installation, VB 20 & 21
START Date:
February, 2011
END Date:
January, 2012 - Prepare & update base line Schedule & Update the schedule weekly basis.
- Identify the critical activities closely monitor to avoid the delay on the project.
- Closely monitor the procurement of the material to maintain the baseline without any impact.
- Issue the weekly target on the floor layout to the project team
- Prepare weekly and monthly progress reports to main contractor.
- Attend progress meetings with main contractor and engineers.
- Issue 2weeks look ahead to site team to identify the forecast activities to align the baseline target.
- Update & monitor Engineering & Procurement Registry.
- Identify the main contractor delays & issue and report to Planning manager for further action
- Identify our delays and give the recovery plan to recover the delay.
- Issue an internal target program to the project team and monitor weekly basis.
- Identify concern & issues and report to planning manager and maintaining the logs.
Experience Hours (Planning & Scheduling):
2000
Experience Hours (Cost Management):
300 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Project Engineer, SAMAACO INT.ENG. CONSTRUCTION, EPIC for Strategic Gas Transmission (Roads & Associated Work)
Project Engineer, SAMAACO INT.ENG. CONSTRUCTION, EPIC for Strategic Gas Transmission (Roads & Associated Work)
START Date:
December, 2009
END Date:
January, 2011 - Plan the project, allocate resources and manage the project load.
- Prepare the baseline program and update the schedule weekly basis
- Coordinate with main contractor to avoid miss-communication
- Provide technical ideas to our technical team
- Preparing the interim bills and dealing with quantity measurement with the client representative.
- Handling of technical problems at the site.
- Implementation of safety procedures & environmental plans.
- Organize site work day by day according to the site condition & laboratory and field tests.
Experience Hours (Planning & Scheduling):
2000 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Quantity Surveyor, Natural Homes-Building Construction & Engineering (PVT) Ltd, Sri Lanka , Housing Project- Multipurpose Building( Civil & MEP Works)- UNESCO-Sri Lanka
Quantity Surveyor, Natural Homes-Building Construction & Engineering (PVT) Ltd, Sri Lanka , Housing Project- Multipurpose Building( Civil & MEP Works)- UNESCO-Sri Lanka
START Date:
July, 2007
END Date:
March, 2009 - Prepare the project progress and update on a monthly basis
- Prepare & monitor the Procurement control registry.
- Preparation and valuation of progress and final payments
- Review the subcontractor & supplier valuation of progress and final payments
- Preparing the weekly progress reports
- Identify & evaluate the variations scope.
- Attend the progress meetings.
- Evaluates the quotation from suppliers/ subcontractor against the estimated budget.
- Review job cost with Project Management team and highlight any subcontractor/material vendor changes
Experience Hours (Planning & Scheduling):
2000
Experience Hours (Cost Management):
3200 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Elevator Engineer, ETA-MELCO ENGINEERING (PTE) LTD, The Monarch Apartment (2B+30+R) - 4 Elevator Installation
Elevator Engineer, ETA-MELCO ENGINEERING (PTE) LTD, The Monarch Apartment (2B+30+R) - 4 Elevator Installation
START Date:
July, 2006
END Date:
April, 2007 - Preparation of work schedules for installation of elevators.
- Prepare & monitor the Project cost control.
- Pre installation works coordination with contractor.
- Co-ordinate with workers, customers to achieve time bound targets.
- Interacting with clients, consultants and contractors for requirements at site and attending regular meeting.
- Monitoring and tracking the project status along with safety and quality checks.
- Sending “correspondence letter” to clients, consultants and contractors.
- Guide and motivate the workers to maintain the quality standards / safety standards during the installation.
- Analyzing the technical problems at site and providing the solutions.
- Monitor expenditure of projects and provide information to prepare invoices and valuation certificates.