Mohamed Fazl's experience

ANALYST / PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection & WWTP

ANALYST / PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection & WWTP

START Date: 
April, 2012

Project Planning, Executing, Monitoring & Control & Close out

  • Review tender documents and prepare pre-contract planning package as per tender requirements
  • Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
  • Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
  • Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
  • Develop the WBS & WP (Scope baseline) to manage & control as per scope.
  • Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI)  and notify to the project manager to control the variance.
  • I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
  • Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
  • Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
  • Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
  • Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
  • Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
  • Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
  • Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
  • Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
  • Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
  • Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
  • Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
  • Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule. 

 

Reporting

  • Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
  • Prepare & submit the EVM report to the management
  • Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
  • Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
  • Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
  • Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.

 

ERP-Oracle-EBS

  • Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
  • Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
  • Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
  • Develop new reports as when required and randomly check the retained cost by finance department
  • Highlight the ERP Project related issue to IT department
  • Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
6000
PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection

PLANNING ENGINEER, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection

START Date: 
April, 2012

Project Planning, Executing, Monitoring & Control (Time, Scope & Cost)

  • Review tender documents and prepare pre-contract planning package as per tender requirements
  • Attend the Kick-Off meeting and discuss the Deliverables, Milestones, Concern & Risk Area, Permit to Work (PTW) and etc.
  • Prepare Clause 14/8.3 (Baseline) Program, Project Planning Procedure / Packages and obtain approval from client/engineer & identify the Critical Path activities & forecast critical path on as-built schedule and notify to the Project Manager to control the variance.
  • Issue 2 weeks Look ahead, 1 Month Look ahead program & Internal target program to meet the progress & minimize the variance to the project team
  • Load resource & cost on the baseline program to monitor the resources, cost & progress.
  • Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
  • Prepare Progress  Measurement  System  (PMS),  Equipment  Resource  Planning  (ERP), Manpower Resource Planning (MRP), Cost Control Registry (CCR) & Progress S-Curve (Early Start & Late Start)
  • Update Progress Measurement System (PMS) daily, measure the progress performance from SV & SPI and report to the project manager for further action on the delay.  
  • Identify the delays and prepare the recovery program by crushing or fast track activities to achieve to maintain the baseline WBS completion date.
  • Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
  • Responsible to plan the most efficient way to complete the project as scheduled and within the budget I developed the Cost Control Registry (CCR) along with EVM system and update by monthly and assess the CV, EAC, ETC, VAC & CPI & submit the EVM report to Project Manager & Higher Management.
  • Review the subcontractor baseline schedule and monitor the progress and responsibility to accelerate the progress to complete the on schedule.
  • Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
  • Identify the Project Risk, prepare the Risk Management Plan & monitoring the registry monthly basis
  • Plan the 3 month project wise revenue for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
  • Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I used update the cash flow as per as-build schedule. 

Reporting & Closure

  • Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
  • Prepare & submit the EVM report to the management
  • Prepare & submit daily/ weekly progress summary report to the management.
  • Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
  • Prepare and handle all planning documents for Project Closure.
  • Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow
  • Prepare the company cost report and analyse the annual revenue & profit/loss from the project control department.

 

ERP-Oracle-EBS

  • Responsibility to create the projects in the ERP-Project Modules, task as per WBS, assign the customer & project manager and create the cost budget for the project
  • Give instruction to Supply Chain user to select the proper Item Code and Task to avoid wrong cost booking.
  • Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
  • Develop new reports as when required and randomly Check the cost booked by finance department
  • Highlight the ERP Project related issue to IT department
  • Close the project as per close-out transmittals to avoid to book the cost on the completed project.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
8000
Experience Hours (Forensic Analysis): 
6000
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP

Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP

START Date: 
April, 2011

Project Planning, Executing, Monitoring & Control & Close out

  • Review tender documents and prepare pre-contract planning package as per tender requirements
  • Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
  • Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
  • Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
  • Develop the WBS & WP (Scope baseline) to manage & control as per scope.
  • Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI)  and notify to the project manager to control the variance.
  • I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
  • Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
  • Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
  • Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
  • Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
  • Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
  • Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
  • Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
  • Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
  • Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
  • Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
  • Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
  • Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule. 

 

Reporting

  • Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
  • Prepare & submit the EVM report to the management
  • Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
  • Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
  • Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
  • Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.

 

ERP-Oracle-EBS

  • Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
  • Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
  • Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
  • Develop new reports as when required and randomly check the retained cost by finance department
  • Highlight the ERP Project related issue to IT department
  • Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
6000
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP

Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP

START Date: 
April, 2011

Project Planning, Executing, Monitoring & Control & Close out

  • Review tender documents and prepare pre-contract planning package as per tender requirements
  • Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
  • Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
  • Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
  • Develop the WBS & WP (Scope baseline) to manage & control as per scope.
  • Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI)  and notify to the project manager to control the variance.
  • I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
  • Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
  • Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
  • Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
  • Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
  • Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
  • Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
  • Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
  • Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
  • Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
  • Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
  • Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
  • Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule. 

 

Reporting

  • Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
  • Prepare & submit the EVM report to the management
  • Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
  • Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
  • Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
  • Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.

 

ERP-Oracle-EBS

  • Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
  • Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
  • Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
  • Develop new reports as when required and randomly check the retained cost by finance department
  • Highlight the ERP Project related issue to IT department
  • Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
6000
Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP

Planning Engineer, Peninsular Petrotech Engineering W.L.L, Civil, Mechanical Erection & Cathodic Protection, MEP, PEB Erection, WWTP

START Date: 
April, 2011

Project Planning, Executing, Monitoring & Control & Close out

  • Review tender documents and prepare pre-contract planning package as per tender requirements
  • Attend the Kick-Off meeting and discuss the deliverables, milestones, concern & risk and etc.
  • Prepare the progress measurement procedure, planning procedure, invoicing procedure, costing procedure & risk management procedure as per project scope.
  • Introduced Progress Measurement System (PMS), Cost Control Registry (CCR) and Earned Value Management System (EVMS) to monitor & control the project.
  • Develop the WBS & WP (Scope baseline) to manage & control as per scope.
  • Prepare Clause 14/8.3 (Schedule Baseline) program identify the critical path activities, lags & leads, total float & forecast critical path & update activity performance on time basis, evaluate the schedule KPI (SV & SPI)  and notify to the project manager to control the variance.
  • I develop the schedule baseline by cost loaded or agreed weightage (Specially EPC project) with stakeholders.
  • Identify the new critical activities, logics & sequence & get the confirmation from stakeholders to schedule by progress override to minimize the negative float.
  • Closely monitoring & control the activities to maintain the actual progress in the early-late start envelope.
  • Issue 2 weeks look ahead, 1-month Look ahead program & Internal target program to meet the progress & control the variance.
  • Prepare the Cost Control Registry (cost baseline) for project cost control, update the cost baseline, evaluate the cost KPI (CV, CPI, EAC, ETC, VAC & TCPI) & report to the project manager.
  • Identify the delays and prepare the recovery program by crushing or fast track activities to maintain the completion date.
  • Identify delays event on updated schedule & delay log and prepare the time impact analysis (TIA) for Extension of time (EOT) and revise schedule as approved.
  • Responsible to plan, monitor & control the most efficient way to complete the project as per scope, scheduled and within the budget.
  • Review the subcontractor baseline schedule and monitor the baseline and responsibility to accelerate the project to complete the on schedule.
  • Attend progress meetings on a weekly basis. Beside from providing updates about the project, address progress override when required.
  • Identify the project risk, prepare the risk management plan & monitoring the registry monthly basis
  • Prepare 3-month revenue look ahead for project wise for the company and drive the project manager to achieve the target to maintain the company cash flow & yearly achievement.
  • Prepare & submit project cash flow forecast to finance department to identify the financial risk on the project & I update the cash flow as per updated schedule. 

 

Reporting

  • Prepare & submit monthly progress report (MPR) & weekly progress reports (WPR).
  • Prepare & submit the EVM report to the management
  • Prepare & submit daily/ weekly progress summary report to the management when the project in critical level.
  • Prepare company revenue, WIP (Work in progress) report monthly basis to evaluate the company revenue from the project control department.
  • Issue WIP reports to expedite pending invoice to Project Managers in order to control the Company Cash Flow.
  • Prepare the company cost report and analyze the annual revenue & profit/loss from the project control department.

 

ERP-Oracle-EBS

  • Responsibility to create the projects in the ERP-Project Modules, assign task as per cost WBS, assign the customer & project manager and create the cost budget for the project
  • Give instruction to Supply Chain user to select the proper Item Code and task number to avoid wrong cost booking.
  • Run the project related reports (Monthly reports, performance report, cost card, man-hours tracking report etc.)
  • Develop new reports as when required and randomly check the retained cost by finance department
  • Highlight the ERP Project related issue to IT department
  • Close the project as per close-out transmittals to avoid over cost booking on the completed project.
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
6000
PLANNING ENGINEER, ENERMES ENGINEERING QATAR W.L.L., Pearl Qatar (2B+G+21+R)-MEP Installation, VB 20 & 21

PLANNING ENGINEER, ENERMES ENGINEERING QATAR W.L.L., Pearl Qatar (2B+G+21+R)-MEP Installation, VB 20 & 21

START Date: 
February, 2011
END Date: 
January, 2012
  • Prepare & update base line Schedule & Update the schedule weekly basis.
  • Identify the critical activities closely monitor to avoid the delay on the project.
  • Closely monitor the procurement of the material to maintain the baseline without any impact.
  • Issue the weekly target on the floor layout to the project team
  • Prepare weekly and monthly progress reports to main contractor.
  • Attend progress meetings with main contractor and engineers.
  • Issue 2weeks look ahead to site team to identify the forecast activities to align the baseline target.
  • Update & monitor Engineering & Procurement Registry.
  • Identify the main contractor delays & issue and report to Planning manager for further action
  • Identify our delays and give the recovery plan to recover the delay.
  • Issue an internal target program to the project team and monitor weekly basis.
  • Identify concern & issues and report to planning manager and maintaining the logs.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
300
Project Engineer, SAMAACO INT.ENG. CONSTRUCTION, EPIC for Strategic Gas Transmission (Roads & Associated Work)

Project Engineer, SAMAACO INT.ENG. CONSTRUCTION, EPIC for Strategic Gas Transmission (Roads & Associated Work)

START Date: 
December, 2009
END Date: 
January, 2011
  • Plan the project, allocate resources and manage the project load.
  • Prepare the baseline program and update the schedule weekly basis
  • Coordinate with main contractor to avoid miss-communication
  • Provide technical ideas to our technical team
  • Preparing the interim bills and dealing with quantity measurement with the client representative.
  • Handling of technical problems at the site.
  • Implementation of safety procedures & environmental plans.
  • Organize site work day by day according to the site condition & laboratory and field tests.
Experience Hours (Planning & Scheduling): 
2000
Quantity Surveyor, Natural Homes-Building Construction & Engineering (PVT) Ltd, Sri Lanka , Housing Project- Multipurpose Building( Civil & MEP Works)- UNESCO-Sri Lanka

Quantity Surveyor, Natural Homes-Building Construction & Engineering (PVT) Ltd, Sri Lanka , Housing Project- Multipurpose Building( Civil & MEP Works)- UNESCO-Sri Lanka

START Date: 
July, 2007
END Date: 
March, 2009
  • Prepare the project progress and update on a monthly basis
  • Prepare & monitor the Procurement control registry.
  • Preparation and valuation of progress and final payments
  • Review the subcontractor & supplier valuation of progress and final payments
  • Preparing the weekly progress reports
  • Identify & evaluate the variations scope.
  • Attend the progress meetings.
  • Evaluates the quotation from suppliers/ subcontractor against the estimated budget.
  • Review job cost with Project Management team and highlight any subcontractor/material vendor changes
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
3200
Elevator Engineer, ETA-MELCO ENGINEERING (PTE) LTD, The Monarch Apartment (2B+30+R) - 4 Elevator Installation

Elevator Engineer, ETA-MELCO ENGINEERING (PTE) LTD, The Monarch Apartment (2B+30+R) - 4 Elevator Installation

START Date: 
July, 2006
END Date: 
April, 2007
  • Preparation of work schedules for installation of elevators.
  • Prepare & monitor the Project cost control.
  • Pre installation works coordination with contractor.
  • Co-ordinate with workers, customers to achieve time bound targets.
  • Interacting with clients, consultants and contractors for requirements at site and attending regular meeting.
  • Monitoring and tracking the project status along with safety and quality checks.
  • Sending “correspondence letter” to clients, consultants and contractors.
  • Guide and motivate the workers to maintain the quality standards / safety standards during the installation.
  • Analyzing the technical problems at site and providing the solutions.
  • Monitor expenditure of projects and provide information to prepare invoices and valuation certificates.
Experience Hours (Planning & Scheduling): 
900