Delay Start-up Insurance to cover Anticipated Profit, Revenue in a Delayed Project
3 years 38 weeks ago1. What is Delay Start-up Insurance (DSU)?
Delay in start-up (DSU) cover is designed to secure the portion of revenue which the owner:
- Requires to service debt; and
- Realize anticipated profit.
It provides protection against delays arising from physical damage caused by any type of peril included in the relevant
Primavera P6 export to Excel. How to color WBS level automatically
5 years 22 weeks agoAfter export activity table from Primavera P6 to Excel, it’s very hard to distinguish WBS level.
Primavera P6 export to Excel. How to identify WBS level for activity
5 years 36 weeks agoAfter export activity table from Primavera P6 to Excel, it's very hard to tell this activity belong to what WBS.
How to use Activity Duration Type in Primavera P6
6 years 3 weeks ago(If the image is too big, you can read the original article at this link : https://doduykhuong.com/2018/03/25/how-to-use-activity-duration-type-in-primavera-p6/ )
In Primavera P6, when we assign resource to activity there is a equation:
Original Duration x Units/Time =
What is the difference between Activity type: Task Dependent and Resource Dependent in Primavera P6
6 years 6 weeks agoIn Primavera P6, there are 2 popular activity type: Task Dependent and Resource Dependent.
So what is the difference?
By choosing Task Dependent or Resource Dependent, P6 will choose what calendar it will use for the activity:
- Choose Task Dependent: P6 use Activity calendar for the activity
- Choose Resource Dependent: P6 use Resource calendar for the
How does Primavera P6 calculate Planned Value Cost for Activities without linear distribution (using Resource Curves or Manual plan) in Earned Value Management
6 years 9 weeks agoWhen we use Earned Value Management technique, we focus on:
- Planned Value Cost (PV) = Budget At Completion * Schedule % Complete
- Earned Value Cost (EV) = Budget At Completion * Performance % Complete (usually equal to Activity % Complete)
- Schedule Variance (SV) = EV - PV
- SV > 0 : project is good, ahead of schedule
So Planned Value Cost
How to define Resource Productivity in Primavera P6 and create schedule
6 years 21 weeks agoWhen create a schedule, we can based on Resource Productivity to estimate duration.
For example:
- We have a team which can cast 10 m3 of concrete per day (This is Productivity)
- We have an Foundation which take 100 m3 concrete.
- Duration of Foundation activity will be 100 / 10 = 10 days
Now we will do it in Primavera.
Supposed
How to quickly identify Behind Schedule and Over Budget activity by Indicator UDF in Primavera P6
6 years 28 weeks agoIn Primavera P6, we can quickly identify behind schedule and over budget activity by using graphical indicator in User Defined Field.
I will show you how to do it.
Supposed that we have a project which has baseline. After update progress, we can show these column the see whether an activity is behind schedule:
- BL Project Finish : Activity finish date from Project