Site Project Planner, BASIL READ, De-hoop dam

START Date: 
November, 2012
END Date: 
January, 2014

BASIL READ - Site Project Planner (October 2012 – January 2014)

  • Captured and updated contractual programme progress using P6
  • Monitored schedule progress and earned value progress against baseline plans
  • Prepared and Proposed Corrective action to ensure that Contractual dates are met
  • Prepared and distributed weekly and monthly report according to project WBS such as Procurement, Construction, Method Statements, and Drawings etc.
  • Managed Change management (time and cost impact) based on received revised Drawings
  • Re-sequenced delayed activities and  analysis mitigation solution and prepare narratives 
  • Prepared Project S-curves
  • Time Location representing Progress update
  • Prepared Claims programme using various analytical tools (Impact on Planned vs AS Built vs remaining works)
  • Report writing and determining of the quantum (required allowable time) of delays
  • Managed and Identified Stakeholder involvement and accessed their impact to the Project

Results:

  • Completed first 10km pipe installation
  • Completed first 10km pipe Accessories installation e.g. Air Valves, Pump Shafts etc.
  • Completed 7 River Crossing
Experience Hours (Planning & Scheduling): 
2300
Experience Hours (Cost Management): 
500