Obayashi Corporation

Obayashi Corporation Lead Planner

START Date: 
May, 2007
END Date: 
May, 2008
DUBAI METRO RAIL PROJECT
Detailing of Baseline Schedules as per Client Reqmt
Cost Loading of Program as per Contract BOQ
Daily, Weekly, Monthly Progress Reporting to Client and Higher Management
Monthly Progress Presentations to Client
Assessment of Subcontractors Baseline Schedule
Preparation of Client Invoices using Primavera Cost Loaded Programs
Tracking of Design Consultants Program
Program related assistance to Delay Claim Assessment/Analysis

Obayashi Corporation Planner

START Date: 
May, 2008
Current Role

Obayashi Corporation Planner

START Date: 
April, 2008
Current Role

Wan T C

First Name: 
Wan
Last Name: 
T C
Professional Since: 
Oct-2003 (20.5 yrs experience)
Oldest experience: 
Apr 2008 (16.1 yrs experience, WARNING: 4.4 years variance with Professional Since)
Years Experience: 
0

Obayashi Corporation Planner

START Date: 
March, 2008
Current Role

Sathyaseelan Manodeepan

First Name: 
Sathyaseelan
Last Name: 
Manodeepan
Professional Since: 
Jul-1993 (30.7 yrs experience)
Oldest experience: 
Mar 2008 (16.1 yrs experience, WARNING: 14.6 years variance with Professional Since)
Years Experience: 
0

Planning Engineer (UG Metro Construction Planner), Obayashi Corporation, Phase 2 - Dubai Metro (Greenline Underground Stations)

START Date: 
March, 2007
END Date: 
November, 2008

As responsible Construction Planner, contributed towards the construction of Dubai’s first fully automated Urban Railway Network ‘Metro System’; Dubai Metro Rail Project “Phase II Green Line”, Client- Road & Transport Authority (RTA). Main duties were-  

·   Framed out the work breakdown structure from work scope; identified detailed activities, defined chronological work sequences and interdependencies between activities as per drawings, estimate work duration and manpower resources for developing BL Schedule

Experience Hours (Planning & Scheduling): 
2800
Experience Hours (Cost Management): 
1600
Experience Hours (Forensic Analysis): 
800

Obayashi Corporation Planner

START Date: 
May, 2007
Current Role

rohit Raghavan

First Name: 
rohit
Last Name: 
Raghavan
Professional Since: 
Nov-1999 (24.4 yrs experience)
Oldest experience: 
May 2007 (17.0 yrs experience, WARNING: 7.4 years variance with Professional Since)
Years Experience: 
0

Obayashi Corporation Planner

START Date: 
July, 2006
Current Role

Market Place