Planning Manager

Planning manager, Kier International, Various Shopping Malls & Residential Apartments

START Date: 
November, 2006
END Date: 
May, 2009

Planning Manger for the Mivan-Kier Joint Venture in Romania.
Located in Bucharest and resposible for all planning and production control measures on both current projects and tenders.
Responsible for the recruitment, management and training of 2 local Planning engineers.
Oversaw planning control of Liberty Center Bucharest 1st mall to be built in Romania and open on time within budget.
Currently engaged in pre construction tender planning activities.

Planning Manager, Daiho Corporation, Hsinchu Rail Station, S220, Taiwan High Speed Rail

START Date: 
May, 2004
END Date: 
December, 2005

Planning Manager,

Daiho Corporation,

S220, Hsinchu Station Project, Taiwan High Speed Rail Project.

Planning Manager, Leighton India, Four Lane Road Project between Indore & Khalghat, India.

START Date: 
August, 2006
END Date: 
March, 2008

Planning Manager,

Leighton India,

Four Lane Road Project between Indore & Khalghat, India.

Planning Manager, Al Futtaim Carillion, Al Muneera Project in Al Raha Beach Development

START Date: 
April, 2008
END Date: 
June, 2009

Planning Manager,

Al Muneera Project, Al Raha Beach Development
Abu Dhabi, UAE
 

Planning Manager, Bovis Lend Lease, 125 Old Broad Street

START Date: 
December, 2004
END Date: 
November, 2006

Planning Manger on the 125 Old Broad Street and 60 Threadneedle Street Projects in the City of London for Hammerson.
Pre construction planning on the St Davids Center and Bristol Broadmead shopping centers.

Planning manager, Mace, Tower Place

START Date: 
December, 2000
END Date: 
December, 2002

Planning Manager. Worked on various projects initially Airport work 10year logistic study at Heathrow for BAA. Project Planning Manager at Tower Place.

Planning Manager, Alcatel Lucent M Berhad , Celcom 3G Project Implementation (Phase II)

START Date: 
August, 2006
END Date: 
April, 2008
  • Implement integrated cost and schedule control including baseline development for 3G Rollout for Node B, transmission PDH, SWAP, 2G, IVVR & RNC Implementation Project
  • Provides status updates to schedules, verifies accuracy of work completed and analyzes progress, schedule performance and variances from the plan
  • Support roll-out manager to establish monthly target for Node B, transmission PDH and SWAP Project implementation
  • Provide bi-weekly progress reports to Steering Committee
  • Support the change management by identifying any critical changes to the

Planning Manager, "Tekfen Construction and Installation Co., Inc.", P059 Expressway Project

START Date: 
March, 2007
END Date: 
May, 2017

Extension of Time Claims

Preparation of Work Schedules

Preparation of Monthly management reports

Evaluation of monthly progress reports, master plans

Experience Hours (Planning & Scheduling): 
20500
Experience Hours (Forensic Analysis): 
15000

Planning Manager, Carillion Plc - Transport - London Projects, Rail Projects

START Date: 
April, 2004
END Date: 
March, 2008

Project Planner and Planning Manager for Carillion rail and infrastructure projects

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
5000
Experience Hours (Forensic Analysis): 
500

Planning Manager, KBR, Palm Island Jumeirah Project, Dubai

START Date: 
October, 2004
END Date: 
September, 2008

Project: Palm Island Jumeirah Project, Dubai, UAE.
Contract value approximately £4 billion.
The Program is located on the Jumeirah Beach coastline approximately 20km southwest of the centre of Dubai and comprises of a shore-connected island shaped in the style of a palm tree.