Planning Manager

Planning Manager, PHARMEDULE, New Humalog®Bulk Project Purification Building

START Date: 
October, 2001
END Date: 
September, 2003

Lilly del Caribe, Puerto Rico - Project Schedule Manager (Pharmadule).

Responsible for planning and progress report in the project New Humalog®Bulk Project Purification Building. To analyse the time schedule with the help of Earned Value and CMP and to write reports concerning the current situation for the customer were also parts of the task.

Planning manager, Logmor International, Hospitals UAE

START Date: 
October, 2010

Whilst I appreciate my experience may not be totally dedicated to the requirements of this particular vacancy, I feel there may be an interest in the overall value of my capabilities which can link in to this post.

My current situation has evolved from taking up new ideas last year in terms of the work I do and has proved to be quite an interesting challenge.

I have succeeded in carrying out a number of projects requiring careful analysis from my client’s point of view and have received repeat work as a result. Two examples

Planning Manager, WCT Berhad, Building Construction Project in Qatar

START Date: 
May, 2011

Manage & Control The Project and the planning Department. from executing, monitoring & control, closing.

Planning Manager, RWEnPower, FGD Projects Aberthaw Power Station

START Date: 
March, 2008
END Date: 
December, 2009

Planning Manager on FGD Project at Aberthaw Power Station with RWEnPower.

Monitored Contractors Program, Generated Monthly reports.

Planning Manager, Carillion, Wolverhampton Building Schools for the Future

START Date: 
March, 2011

Managing programmes for various multi million pound projects

Progress Reporting

Managing Risk

Labour calculations

Scaffold Calculations

Planning Manager, EC Harris International Ltd., Department of Transport Programme Management Services

START Date: 
January, 2011

Responsible for developing Standards/ procedures with regards to Schedule management.Strategic Planning Role, Reviewing Contractor/Consultant Schedule. Preparing the overall master schedule.Creating standard Work Breakdown Structure etc. advising client on the benefits of implementing schedule management at project and program level.

Planning Manager, Blair Anderson Limited, Ferrari Theme Park, International City Ph2-3, Port Rashid Demolition, (Claims - Shoreline Apartment, Signature Villas, Adnec Phase 2B Aloft Hotel, Hasdrubal Plant Tunisia , DLC Headquarters and Amenity Buildings,

START Date: 
May, 2007
END Date: 
January, 2011

Responsible for creating and managing schedule from 30 contractors mainly Rides an Attractions, Had to coordinate with the Main Project Managers, Worked for Jack Rouse Associates (Consultants) who hired Blair Anderson to carry out Planning Services.

 

M.A.Kharafi & Sons (Contractor) hired Blair Anderson to carry out Planning Services for the project. Preparing the baseline programme, Monthly programme updates, Preparing Claim notifications, Interim particulars, Correspondence etc. preparing revised programme, time impact analysis, and claim report.

Planning Manager, Tata Realty & Infrastructure Limited, National Highway - NH9

START Date: 
May, 2009
END Date: 
April, 2010

 

M/S. TATA REALTY AND INFRASTRUCTURE LIMITED (JUNE-2009 TO TILL DATE)

Planning Manager, KOU GC, Water Pumping Station

START Date: 
May, 2010
END Date: 
November, 2010

- Coordinate all planning objectives
- Establish and calculate schedules for the purpose of submission
- Monitor and update project schedules
- Determine the critical path and identify potential shifts schedules
- Propose corrective actions
- Establishment of procedures for the planning function
- Participation in technical meetings
- Review of dossiers of  executions
 

Planning Manager, Alstom GRID, Sub Station Transformers

START Date: 
December, 2010
END Date: 
September, 2013

Support project managers throughout the organization to ensure that effective planning and key project controls are in place starting from the initial project planning through the execution phase EPC projects.

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
Syndicate content