PLANNING ENGINEER

Planning Engineer, Wade Adams, Design & Build Project

START Date: 
October, 2006
  • Conceptualize the scope and preparation of phasing plan schedules.
  • Identification of constraints and key milestones.
  • Defining construction methods and formulation of Team productivity.
  • Defining and sequencing of Activities and Activity Duration Estimation. 

Planning Engineer, Kele Contracting, D1 Tower

START Date: 
October, 2008

Kele Contracting

Planning Engineer

D1 Tower Project at Culture Village in Dubai - UAE

PLANNING ENGINEER, Magnox Electric, Nuclear Decommissioning

START Date: 
September, 1987

Based at Hunterston 'A' Nuclear Decommissioning Site, as part of a multidisciplinary team working on a portfolio of complex projects associated with the decommissioning process.

PLANNING ENGINEER, Mainzeal Construction, Project Century

START Date: 
November, 2003

Planning engineer for Mainzeal Construction, currently at Project Century in Auckland

Planning Engineer, SBM Malaysia Sdn. Bhd., Aseng FPSO Project

START Date: 
July, 2007
END Date: 
February, 2011

I've been in Oil and Gas Industry more than 8 years. My first 3 years experience I was involved with fabrication works. It was 12000MT project Central Processing Platform. Furthermore I was moved to SBM Offshore purposely to strenthening my knowledge in deep water project. Covering up EPCIC work scope and performing the ASENG FPSO project (VLCC) frankly It was big challenge I ever had!!!

Planning Engineer, CAT Group, Marina Towers

START Date: 
March, 2004
END Date: 
March, 2006
To develop all planning and scheduling tools to be used in control, monitoring and reporting of project status.

PLANNING ENGINEER, Al Yusr Townsend & Bottum Co., QC/TC/T/18/05 EPIC of C4+ Product Pipe Line to QAPCO for Lab Project. EPIC of Natural Gas Supply Pipeline to Independent Power Plant at AL-UDAID AIR BASE (AUAB). 4)Installation of Independent Power Plant f

START Date: 
November, 2005
END Date: 
January, 2014
  • Study Project Scope, Conduct Workshop with Stakeholders and Clarify Project Requirements, Required Documentation, Detail Project Scope, Duration of Project, Identify Require Deliverables, Milestones.
  • Develop WBS Directory, Milestones List, Activity List, Activity sequence, Estimate Activity Duration, Resources Directory & Work out detailed Resource Requirement (Manpower, Equipment) based on standard productivity norms.
  • Prepare Project Baseline Schedule in coordination with different

Planning Engineer, Frayland Construction and Interiors LLC, Dubai Festival City

START Date: 
July, 2005
END Date: 
March, 2008

• Preparing project activity time schedule for execution as well as for tender.
• Preparing Clause 14 baseline programme.
• Resource planning and progress S-Curve.
• Analysing delay events and preparing Extension of Time claim programmes.
• Attending the meetings with the Suppliers, Subcontractors, Client & Consultants regarding
progress and time related issues.
• Reporting critical issues to the management.
• Preparing presentations & reports for the client.  

Planning Engineer, Binladin Contracting Group, Burj Views, 3-Towers (3Basements+Ground + 40 Levels), Emaar Project

START Date: 
March, 2007
END Date: 
February, 2009

Planning Engineer at Burj Views (3-Towers) (3Basements+Ground + 40 Levels), Binladin Contracting Group (L.L.C),(Dubai)