Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

PLANNING ENGINEER

Planning Engineer, Joannou & Paraskevaides, GOSP (Gas Oil Separator Plant)

START Date: 
August, 2007
END Date: 
September, 2008

Employer : JOANNOU AND PARASKEVAIDES (SAUDI ARABIA) LTD.
Employment Date : Sept. 16, 2007 – Sept. 30, 2008
Position : Planning Engineer
Project : Nuayyim ASL Crude Increment Facilities
Client : Saudi ARAMCO

1.“planning engineer” or “project planner”, J.N.Bentley & Co Ltd, YWS AMP5 Projects

START Date: 
April, 2010
END Date: 
July, 2012

Planner supporting project teams and batch managers in preparing, updating and monitoring their project plans to the requirements of NEC3. Included preparation of schedules, training of Batch Managers in P6 and preparation of templates to assist set up of new projects. Key client liaison on planning and schedules working with NEC PM's to ensure compliant programmes and accurate updates and EVA information.

Planning Engineer, A Jaber LLC, Fixing Wadi Project

START Date: 
August, 2006
  • Preparing the Master Programme of Works for various Projects with the scope in Sewerage, Storm Water, Water Works, Irrigation, Electrical, Telephone, Road Works, Substation, Irrigation Reservoir/Pump Station, other essential utilities, Highways, Parking, Landscaping, Brdiges, and Airport.
  • Prepare monthly reports, weekly reports, daily reports and night shift report.
  • Update of Over-All Programme of works, 60-days look ahead and 3-weeks look ahead.
  • Prepare and submit the project status report, equipment and manpower.
  • Prepare and submit updated/re

Planning Engineer, Overseas-AST co. llc., Dubai world central international airport Jebel ali

START Date: 
January, 2006
END Date: 
August, 2008

Project planner and area field engineer for Aviation jet fuel pipeline and hydrant system for Dubai world central international airport Jebel ali

PLANNING ENGINEER, M N Dastur & Company (P) Ltd., Construction of thermal power plants

START Date: 
March, 2004
END Date: 
August, 2008

Planning in MS Projects & Primavera P6

Reporting Progress

Coordination with site office and engineering office

Planning Engineer, CCC-TAV JV, Pipeline / Aviation / Building

START Date: 
February, 2007

Planning, Scheduling, Claims, Contract Administrative works for planning, Coordinate material and constructions drawings as per baseline schedule, Baseline/As-Built programme comparison, Plan the pre-constructions works & permits.

Experience Hours (Planning & Scheduling): 
600
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
300

Planning Engineer, EIED, Hormuz oil refinery Plant (EP) Consortiums: EIED Co. , OIEC Group, ODCC Co.

START Date: 
April, 2004
END Date: 
August, 2009

 

Tasks:

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content