NEWS - One or two users are experiencing intermittent problems with Internet Explorer Version 10, if you have problems entering data, for now, please try a different browser. Sorry :(

Power Generation & Nuclear

K L KAMESWARI AKONDI

First Name: 
K L KAMESWARI
Last Name: 
AKONDI

Primavera Software:My comapny has given a training in Primavera Software.We can create a Unlimited baseline in Primavera.I worked in 2X685 MW Super critical Power Plant.Every Month Contractor is sending the Primavera File to us.I am uplloading the document in Primavera and assigning the Baseline to it and then i will update Schedule and Tracking the schedule ,identifying the Critical path

MS Project:It is the Basic tool before learning the Primavera.In my project Package(WTP, RWI,CHP,AHP ) vendors submitting schedule through MSP only.So every month i am updating the small

Professional Since: 
Feb-2011 (2.4 yrs experience)
Oldest experience: 
Feb 2011 (2.4 yrs experience)

Junior Manager, GMR Energy Ltd, 2x685 MW Super Critical power Plant

Project:

  • GMR Chhattisgarh Energy Limited, Raipur is a 2x685 MW Thermal Power Plant located near Raikheda, Chhattisgarh.

 

Job responsibilities:

  • Developed an Excel based Monitoring sheet for Engineering, Procurement and Construction for generating the S-curves.

 

  • Preparation, Updating of L2 Schedule Plan of Various Packages in Primavera(P6 version).

 

  • MIS report generation to the top management & Preparation of Project progress S-c
Experience start date: 
February, 2011
Map picker: 

EPC Senior Planner, Alstom Power, Several Power Generation Projects

Senior Lead Planner supporting Tender and Execution team in several projects

. - Definition of database structure in P6, WBS, Activity coding, Resource and costs loading. - Baseline projects. - Implementing reporting: Progress reports, KPI, S-Curves. - Critical Path Analisys - Coordination between Project partners/Consortium -

Experience start date: 
January, 2013
Map picker: 

EPC Senior Planner, Alstom Power, Several Power Generation Projects

Senior Lead Planner supporting Tender and Execution team in several projects

. - Definition of database structure in P6, WBS, Activity coding, Resource and costs loading. - Baseline projects. - Implementing reporting: Progress reports, KPI, S-Curves. - Critical Path Analisys - Coordination between Project partners/Consortium -

Experience start date: 
January, 2013
Map picker: 

etienne kervil

First Name: 
etienne
Last Name: 
kervil

Tony Old

First Name: 
Tony
Last Name: 
Old
Professional Since: 
Aug-1989 (23.9 yrs experience)
Oldest experience: 
Feb 1996 (17.4 yrs experience, WARNING: 6.5 years variance with Professional Since)
Guild Accreditation: 
None

Yashwant Mishra

First Name: 
Yashwant
Last Name: 
Mishra

 

 Senior Planning Engineer:

Duties & Responsibilities

  • Assist Area Manager/Project Engineer in development of Level 4/5 detailed construction Schedule.

 

  • Monitor Level 4/5 Schedule implementation and generate out-of-sequence activity report.
  • Directly responsible to the Planning & Controls Manager in maintaining the Primavera P6 C
Professional Since: 
Jul-1990 (23.0 yrs experience)
Oldest experience: 
Jan 1998 (15.5 yrs experience, WARNING: 7.5 years variance with Professional Since)

Senior Planning Engineer, DTMT Construction, Newman, Western Australia, Yarnima Power Station project

Duties & Responsibilities

  • Assist Project Manager in updating detailed construction Schedule.
  • Work out what if analysis.
  • Produce Weekly and Monthly Construction progress including P6 Gant Bar chart, progress ‘S’ Curves, Histograms as per the guidelines of the Client.
  • Record all relevant project Data.
  • Provide and share planning expertise with Project Controls team.
  • Execute duties in accordance with Planning systems and procedures
Experience start date: 
October, 2012
Map picker: 

Senior Planner, British Nuclear fuels, THORP Nuclear Plant

Senior Planner- British Nuclear Fuels (BNFL), Sellafield UK £1.5 billion Nuclear Reprocessing facility. Multi discipline planning role.

Experience start date: 
June, 1985
Experience end date: 
October, 1990
Map picker: 

Mark von Leffern

First Name: 
Mark
Last Name: 
von Leffern

Mark has 12 years’ experience in project management and controls primarily in support of large government contracts compliant with ANSI/EIA 748 EVMS standards. His drive to obsess and improve processes and work flow is contagious. His interpersonal and communication skills to formulate and articulate contractual, technical, financial points to the team are unparalleled. Mark has a strong understanding of team dynamics and is passionate about encouraging employees to exceed expectations.

Professional Since: 
Oct-2000 (12.7 yrs experience)

Market Place

The toolkit provides advanced analytical tools which can help identify areas of poor schedule quality at the click of a button.
Maxim Recruitment – Recruiting Construction, Engineering & Planning Professionals Worldwide in the Infrastructure, Rail, Building and Property Sectors.
A comprehensive product suite with the flexibility to meet the varying needs of everyone involved in running projects
We want to build software that solves real problems, allow people to work more productive and happier.
EVA18 is the major UK event for Project Control knowledge, know-how and networking. EVA is a conference organised by a project management practitioner for project practitioners and stakeholders
Syndicate content