START Date:
November, 2005
South Sumatra - West Java (SSWJ) 32" Offshore Gas Pipeline Project - CP2.
- Preparing schedule and pipe loading scenarios to be implemented in relation to daily single joint welding productivity and barge window of availability using P5;
- Preparing transport barges schedule and sequences related to number of available barges and required traffic arrangement during pipelaying activity;
- Preparing pipes coating and thickness identification report;