Hi All
I was just reading the primavera help and came across three different fields:
Start
Planned Start
BL Project Start
I have a question about the following picture, why is there difference between " Planned Start" and " BL Project Start"? Don't they come from the same source which is Project Baseline?
Aren't they the same?
Why is there difference between them? There are some activities that they are exactly the same ( I mean planned start and BL Project Baseline, and there are activiteis where they are different.)
Thanks for your help.