Dear Friend ,
i am working on project which has been delayed from start as the work from hold by the client in the beginning.
The baseline was approved , however after the resumption of work the contractor made a new schedule by changing , adding , deleting some activities in the schedule .however the said schedule was not approved by the client since the client didnt agree on completion date . however the client allow use of it to monitor site progress .
Now at the end of project , in order to make retrospect analysis which schedule should be updated .
the problem is baseline is not reflecting the actual work
Please advise