Hello,
I have a major scheduling project with a client, and I need an efficient way to input Resource data into P6 Professional. I would like to have the client provide a Microsoft Excel Spreadsheet of resource data and then import this into P6 Professional.
Unfortunately, P6 Professional does not read data in the spreadsheet that has a column heading including a (*). This means it will only import the below variables.
Resource ID
Resource Name
Unit of Measure
Default Units/Time
Budgeted Units
Unfortunately, P6 Professional will not read the below variables with column heading including (*).
Resource Type
Role ID
Roles
Max Unit/Time
Standard Rate
Internal Rate
External Rate
Any ideas on an efficient way to import Microsoft Excel resource data into P6 Professional?
Any input?
--Steve