I need some explanation on manhours calculation for resource loading for p6 and MSp
As for my understanding, in p6 the manohurs is called - Budgeted Labor Unit
And for MSp it is called work hour
Quest 1 - Is my understading correct for the above?
Before we come out with the manhours for each activity in the schedule. we must have the productivity for each activity.
Production rate = Qty / unit time
Productivity = manhours / production rate
Estimated manhours = productivity * material qty
Quest 2- Is the above formula correct?