Hi All,
Need some information.
We have been awarded a Project and the Project Manager wanted to show a Level 3 schedule to the Client but internally he wants a Level 4 schedule.
So should I have to make 2 schedule ie Level 3 and Level 4 or can I srink a Level 4 schedule to Level 3.
There would be many Engineering deliverable/Activity in Level 4 Schedule which we dont want to show to Client.
Please advice
Warm Regards
Jithin