I am currently in discussion with my ECCPM regarding an EOT claim. He has issued an instruction that was a few days before a monthly submission. The previous month programme was already accepted. To establish the EOT claim I used the previous month programme as a baseline to the delay, considering this was the last accepted programme.
The ECCPM is asking for the last accepted programme to be updated as an as-built to the date of the instruction.
This seems to go against the contract, so I'm looking for any advice regarding this subject.