Today I received a schedule file that had a couple of references to a storage not found.
I found the first reference was in the previous version used for comparison, a not so obvious issue. I set resource leveling option to previous version and erased the reference. Then got back to the resource leveling option and re-set to original setting - advanced.
I got a second reference to a Baseline not available in my computer and fixed it by setting the current schedule as the baseline. The solution was obvious.
- Is there an easier way?
- If not could it be programmed for user to select to erase the reference within the dialog box?
Best Regards, Rafael