I have a schedule in P6, with Negative floats (-20d)and High Total Float (in 3 digits). There are only 2 constrainsts I have applied. As per Fuse score, the high float and negative float is impacting the most. The constraint score is green. Its almost 1800 line item schedule. How can I go about resolving this. Appreciate a quick response, this being urgent for me to deliver.