Hello,
Can i know if there is a way to hide the non working days using P6? For example
- Working day = Monday to Friday
- Saturday and Sunday are not working day
Activity A F/S Link to Activity B.
Activity A finish on Friday.
Activity B start on Monday because Saturday and Sunday are non-working day.
however, there is a gap on my programe betwen these 2 activities because of Sat and Sun weekend. How do i just hide the non working days so people wont asking all these questions?
Many thanks
Mike