Hi,
Is there a way of getting a Resource Usage Profile Histogram to show what % of a resource has been allocated?
My scenario is each PM can run 4 projects max, we have an LOE in each project with the PM allocated @ 25% so we want to be able to see if we have under/over-allocated the resource and by what percent.
I have been fiddling with the Resource Usage Profile Options, mainly the Calculate average option as I thought it was through that I could get the graph to show as a representation of 1 being max and 0.75/0.5/0.25 to show an under allocation but for the life of me I can't get it to show.
Any help would be appreciated.
Thanks