Hi
Track my project progress;
Status tab
Example: Activity Original Duration 10 days
Tracking: Remaining duration 4 days
Schedule past 10 days
At complete 14 days
Why the % complete is 60% (related to original duraton) instead of 71% (10/14 10 days worked in a new total duration of 14 days)???