HI,
I have prepared schedule for building and assigned cost also but while after updating more than 50% of work as completed, parent WBS is at 11% only.
Task Name | Baseline Duration | Baseline Start | Baseline Finish | Cost | Predecessors | % Complete |
Schedule for Anchorage Building | 1463 days | Wed 06-12-17 08:00 | Thu 29-09-22 17:00 | ₹ 2,455,692,677 | 11% | |
Structural work | 1165 days | Wed 06-12-17 08:00 | Wed 06-10-21 17:00 | ₹ 1,180,088,110 | 100% | |
Sub Structure- Tower | 337 days | Wed 06-12-17 08:00 | Wed 16-01-19 17:00 | ₹ 265,569,460 | 100% | |
Sub Structure- Podium | 486 days | Thu 29-03-18 08:00 | Tue 05-11-19 17:00 | ₹ 78,952,180 | 100% | |
Super Structure | 857 days | Wed 12-12-18 08:00 | Wed 06-10-21 17:00 | ₹ 835,566,470 | 100% | |
Non Structural work | 932 days | Wed 04-09-19 08:00 | Thu 29-09-22 17:00 | ₹ 1,031,195,775 | 0% | |
Masonary & Finishing works | 927 days | Wed 04-09-19 08:00 | Fri 23-09-22 17:00 | ₹ 955,715,719 | 0% | |
Handing Over | 171 days | Fri 11-03-22 08:00 | Thu 29-09-22 17:00 | ₹ 75,480,056 | 0% | |
Other | 1460 days | Wed 06-12-17 08:00 | Mon 26-09-22 17:00 | ₹ 244,408,792 | 0% | |
Professional fee | 1165 days | Wed 06-12-17 08:00 | Wed 06-10-21 17:00 | ₹ 27,879,240 | 4SS | 0% |
Escalation | 1130 days | Mon 09-07-18 08:00 | Thu 31-03-22 17:00 | ₹ 148,073,740 | 4SS+180 days | 0% |
Contingencies | 1460 days | Wed 06-12-17 08:00 | Mon 26-09-22 17:00 | ₹ 68,455,812 | 4SS | 0% |