Hi All,
I've having an issue where in reporting SPI, My planned value is zero just happens to be zero this month, and my earned value is 2.7%, so of course my SPI figure is calculated as 0.00, which in formula world, is the correct answer.
However, in reality, I know this particular phase has earned 2.7% more than planned, and I would like the SPI figure to reflect this.
Anyone know another way to get an SPI figure to reflect this??