Good day,
how I can calculate the % complete of the project when I have the quantities increased from the baseline ???
if I want to consider the actual completed work for some items and it almost reached the baseline or BOQ quantity, this will give a wrong indication of the project % complete.
which numbers I should consider??
regards,