In my project, There are three WBS.
The first and third WBS are about project start and finish procedures. And the second WBS is about all project works of different desciplines.
Is there any possible technique in P6 to identify the total float based on 2nd WBS start and end dates, not on the basis of entire project.
Thanks in advance.