Dear all,
If for example I have one activity that has been commenced on the 4th of Dec, then the activity was paused on the 6th, afterwards it has been proceeded again on the 12th of Dec and totally finished on the 18th of Dec, how can I reflect that gap of the current case on the actual units in the resource assignment? my file divides the total number of hours equally on each day which is not correct. Kindly advice what to do
Thanks a lot
Suhaib