Dear All,
We have 4 delay events in our project. First event has currently an impact of 124 days delay and is still not completed and it is the Client's reponsibililty of the delay. The other three events have been finalized and awarded 60 days EoT by the Client and stated by the Client the following, "The (60) days EoT shall cover any delay in the project prior the date of signing this document. As for delay event No.04, the (60) days shall be part of any claim in the past or future (any time-related claim conerning delay event No.04 shall consider the above 60 days as a grace period to the benifit of the client)".
The Client is instructing the Contractor to submit a revised Baseline Programme for the project considering the Actual Progress prior the date of this document and the additional 60 days related to the above mentioned delay events No.01, 02 & 03 which shall be added to the contractual completion date.
The issue is, how can the contractor submit a revised baseline programme with the instructions of the Client above while he still has (124-60 = 64) days delay not covered? In other words, how the contractor can keep his right of the the (64) days delay by following the Client's instruction?
Thanks.