Hello,
I am putting together a short term schedule with multiple operations on a highway that requires traffic closures each night. Each activity is specific in which direction traffic needs to be closed.
If it were only one operation, I would consider assigning the lane closures as resources. (i.e. a northbound closure for road replacement, striping, etc. in that direction, and one for the southbound direction.) Then I could print a resource usage profile to show what closure we need to plan for.
For multiple concurrent operations, I can't wrap my head around how to assign a resource that would allow me to level the schedule and allow for only one traffic closure direction at a time. Any ideas?
Thanks,
Greg