When dealing with Date Variance it might be convenient to have the following options.
- Days vs Hours - some jobs are scheduled by the hour, some jobs use workdays with different hours.
- Date difference vs. Activity Calendar - at times it is of interest to follow date difference, at times it makes sense to follow difference using activity calendar, at times it is good to compare both. [1]
This can be done if using user defined fields and some formulas but I wonder if there is a direct way I might be missing.
Best Regards,
Rafael