Sometimes the need arises for a schedule made up of selected activities from various other schedules (dynamically linked of course). But so far the only way workaround I could come up was by creating a master (inserting sub projects) and then using filters/flags etc and saving that view.
Is their a more direct way to do this : where MS Project lets you select which activities to insert from a subproject ?