What would the best way to import status in P6 be. Almost all activities will be "physical %".
How do I ensure the status gets logeed in accurately. Many a times when I export a spreadsheet out from P6 and import it back with updated status (% complete, RD, Actual Date), I still end up messsing up certain values. So wanted to check if there was a fool proof way of achieving this simple task without manually having to type it all in.