Hi anyone can help me regarding the subject matter.
I got the xer.file (P6) from our subcontractor with resource loading. however, when I importing the s/c schedule to my P6 the resource loading does not match on his resources. What i'm saying is he has a foreman, mason, carpenter but on my schedule (importing from his xer.file) it doesnt show its different resource is loading.
can anyone advise me how to do this? by the way i'm using P6 version 16.1.
Thanks,
chris