I am analysing a program for a dispute. The dispute occured part way through the project so the delays are retrospective but the impact is prospective.
My client, I beleive by accident changed a calendar for a future few activities from a 24x7 to a 8hr/day calendar. Effectively slipping the program by a sizeable chunk of time. Can this calendar be corrected back to 24x7 for an arbitration? will the arbitrator accept such a major correction?
Thanks,
Regards,