I am updating my program on a weekly basis. Since my project is late my milestone dates are being delayed. The maximum delay for each milestone compared to the previous update should not exceed 7 days (since I am updating on a weekly basis). However, this is not the case; one of milestones got delayed for 9 rather than 7 days. How can my milestone be delayed more than 7 days if only 7 days had passed ?
Any ideas ?
Thanks
Mike